Target station T40 installed in target chamber September - December 2005
(see also the pictures of the T40 installation in the laboratory)  
   
 

 

 

 

 

 

 

13 September 2005: start of target station shielding installation

   
 

 

 

 

 

 

 

10 October 2005: Target station shielding and support frame installed

   
 

 

 

 

 

 

 

10 October 2005: Target station shielding and support frame installed

   
 

 

 

 

 

 

10 October 2005: View through target station into horn area; in the background the Helium Tank No. 1 

   
 

 

 

 

 

 

 

4 November 2005: View through target station onto the recently installed horn

   
 

 

 

 

 

 

 

28 November 2005: insertion of alignment table with target magazine

   
 

 

 

 

 

 

 

 

 

28 November 2005: insertion of alignment table with target magazine

   
   
 

 

 

 

 

 

 

1 December 2005: end of proton beam line and upstream part of target station collimator

 

 

 

 

 

 

 

6 December 2005: frame carrying the target station roof shielding in "open" position

   
 

 

 

 

 

 

 

6 December 2005: motorizations installed and tested

   
 

 

 

 

 

 

 

6 December 2005: Exit side of target magazine and horn upstream end