Horn and Reflector pulsing in final
configuration - 3 March 2006
Following the installation of
the powering systems at the surface, the pulse transformers in the service
gallery and the horn and reflector in the target chamber, first tests with
power have been performed. The reflector was first used with nominal 180
kA double-pulses on 28 February, the horn was pulsed with 150 kA double
pulses on 2 March. No interferences were observed when pulsing both
systems together on 2 and 3 of March. A
report on these tests is available (in French).
|