|
|||||||||||||
Project Overview | Beam Performance | CNGS↔LNGS | Publications/Talks | Events | Links | ||||||||
Technical Page (EDMS) | Civil Engineering | Naming Conventions | Download Pictures | Planning | Search | ||||||||
Project Organization: Secondary Beam WG, Project Team, Technical WG, Commissioning WG |
Progress of works for general infrastructure - November / December 2004 Following the completion of the main civil engineering works and some additions to the underground structures (trenches, holes for air-cooling ducts, etc.), the works for the infrastructure (air handling, water cooling, electrical installation) started in July 2004. The pictures below intend to illustrate some of the progress made since then. (Photos: S. Lebrun, M. Wilhelmsson, K. Elsener) Details on TT41-TCC4 pipework
|
|
Access Gallery TAG41, test section |
|
Access Gallery TAG41, 17 Dec. 2004 |
|
Access Gallery TAG41, 17 Dec. 2004 |
|
Ventilation chamber TCV4, 17 Nov. 2004 |
|
Arrival of metallic structure outside BHA4 |
|
Ventilation chamber TCV4, 26 Nov. 04 |
|
Proton beam tunnel TT41, view downstream |
|
Proton beam tunnel TT41, view upstream |
|
Proton beam tunnel TT41, 17 Dec. 2004 |
|
Target chamber TCC4 |
|
Target chamber, air-cooling ducts |
|
Service gallery TSG4, air cooling unit |
|
Service gallery TSG4, main duct for air to TCC4 in the centre, air cooling units to the right of the tunnel |
|
Special ducts, stored in ventilation chamber, 17 Dec. 2004 |