|
|||||||||||||
Project Overview | Beam Performance | CNGS↔LNGS | Publications/Talks | Events | Links | ||||||||
Technical Page (EDMS) | Civil Engineering | Naming Conventions | Download Pictures | Planning | Search | ||||||||
Project Organization: Secondary Beam WG, Project Team, Technical WG, Commissioning WG |
Horn-1 installation (test-horn) | November 2005 |
2 November 2005: arrival of the horn from the assembly lab to the BHA4 surface building |
|
2 November 2005: Horn unloading |
|
2 November 2005: Horn stored in the surface building BHA4 - with the DBS transport team |
|
3 November 2005: Horn being lowered onto the transport vehicle |
|
3 November 2005: Horn being lowered onto the transport vehicle |
|
3 November 2005: Horn arrives in the target chamber |
|
3 November 2005: Horn transport with the crane in the target chamber |
|
3 November 2005: Horn transport with the crane in the target chamber |
|
4 November 2005: Horn installed (view through the target station shielding, before the installation of the target station collimator and the target magazine) |
|
10 November 2005: Provisional installation of the first stripline segment near the horn |
|
22 November 2005: Horn stripline in the trench and the side gallery (seen from target chamber) |
|
25 November 2005: Horn and stripline installation completed |
|
25 November 2005: Horn striplines support table (near the horn) |
|
25 November 2005: Horn striplines as seen from the service gallery |
|
10 November 2005: Test of transport and installation vehicle for the horn transformer |
7 December 2005: Horn transformer transport |
|
7 December 2005: Horn transformer installed |
|