Target station T40 installed in target chamber | September - December 2005 |
(see also the pictures of the T40 installation in the laboratory) | |
13 September 2005: start of target station shielding installation |
|
10 October 2005: Target station shielding and support frame installed |
|
10 October 2005: Target station shielding and support frame installed |
|
10 October 2005: View through target station into horn area; in the background the Helium Tank No. 1 |
|
4 November 2005: View through target station onto the recently installed horn |
|
28 November 2005: insertion of alignment table with target magazine |
|
28 November 2005: insertion of alignment table with target magazine |
|
1 December 2005: end of proton beam line and upstream part of target station collimator |
|
6 December 2005: frame carrying the target station roof shielding in "open" position |
|
6 December 2005: motorizations installed and tested |
|
6 December 2005: Exit side of target magazine and horn upstream end |
|