TJ8 and Proton Beam Tunnel TT41 | July - December 2005 |
TT41 with magnet transport vehicle |
|
TT41, positioning of MBG magnet |
|
|
|
TJ8, 10 October 2005 (left: TT41 proton beam to CNGS, right: TI8 proton beam to LHC) |
|
TT41, 10 October 2005 (MDG corrector, QTG quadrupole and tilted MBG dipoles) |
|
TT41, 14 October 2005 (supports for QTL and QTS quadrupoles) |
|
TT41, 18 October 2005 (QTL installation has started) |
|
TT41, October 2005 (QTL and QTS installation completed) |
|
19 July 2005: BTVG ready for installation (Optical Transition Radiation profile monitors) |
|
TT41, 10 November 2005 (BPG position monitor, BTVG profile monitor and vacuum equipment installed) |
|
TT41, 1 December 2005 ( vacuum installation completed - last BPG position and BTVG profile monitor, followed by a Be exit window upstream of the BN target collimator)_ |
|