TJ8 and Proton Beam Tunnel TT41 July - December 2005
   
 

 

 

 

 

 

TT41 with magnet transport vehicle

   
 

 

 

 

 

 

TT41, positioning of MBG magnet

   
 

 

 

 

 

 

TT41, last MBG installed, 21 September 2005

   
 

 

 

 

 

 

TJ8, 10 October 2005 (left: TT41 proton beam  to CNGS, right: TI8 proton beam to LHC)

   
 

 

 

 

 

 

 

TT41, 10 October 2005 (MDG corrector, QTG quadrupole and tilted MBG dipoles)

   
 

 

 

 

 

 

 

TT41, 14 October 2005 (supports for QTL and QTS quadrupoles)

   
 

 

 

 

 

 

 

TT41, 18 October 2005 (QTL installation has started)

   
 

 

 

 

 

 

 

TT41, October 2005 (QTL and QTS installation completed)

   
 

 

 

 

 

 

 

19 July 2005: BTVG ready for installation (Optical Transition Radiation profile monitors)

   
 

 

 

 

 

 

TT41, 10 November 2005 (BPG position monitor, BTVG profile monitor and vacuum equipment installed)

   
 

 

 

 

 

 

TT41, 1 December 2005 ( vacuum installation completed - last BPG position and BTVG profile monitor, followed by a Be exit window upstream of the BN target collimator)_