News

 

3/12/2012

End of CNGS run

6-10/11/2012

8th NBI2012 workshop at CERN

31/05/2010

First tau-neutrino candidate detected

Project Overview Beam Performance CNGS↔LNGS Publications/Talks Events Links
Technical Page (EDMS) Civil Engineering Naming Conventions Download Pictures Planning Search
 
Project Organization:  Secondary Beam WG, Project Team, Technical WG, Commissioning WG


Progress of works for infrastructure and equipment installation
July 2005

Following the completion of the main civil engineering works and some additions to the underground structures (trenches, holes for air-cooling ducts, etc.), the works for the infrastructure (air handling, water cooling, electrical installation) started in July 2004. Progress until the end of 2004 has been reported previously. The pictures below illustrate some of the work done between January and July 2005. (Photos: M. Brice, S. Girod, G. Maire, T. Reynes, S. Lebrun, M. Meddahi, A. Pardons, M. Wilhelmsson, K. Elsener).

Proton Beam Tunnel   Access Gallery   Horn Power Cables    Ventilation Chamber

Target Chamber   Helium Tank Installation    Service Gallery   Target Station T40

 

   
Surface  
   
 

 

 

 

 

 

 

 Surface, January 2005

   
   
Cavern ECA4  
   
 

 

 

 

 

 

 

 Welding team on scaffolding in ECA4 cavern,  May 2005

 

 

 

 

 

 

 

 ECA4 pipes and ducts, July 2005

   
   
Ventilation Chamber TCV4  
   
 

 

 

 

 

 Ventilation units installed on the upper level of   the ventilation chamber, February 2005

   
 

 

 

 

 

 

 Ventilation chamber, upper level, May 2005

   
   
Service Gallery TSG4  
   
 

 

 

 

 

 

 One of four air-cooling units installed in the  service gallery, 25 February 2005

   
 

 

 

 

 

 

 

 Service Gallery, 25 February 2005

   
 

 

 

 

 

 

 

 Service Gallery TSG4, May 2005

   
 

 

 

 

 

 

 

 Service Gallery, 1 July 2005

   
 

 

 

 

 

 

 Service Gallery TSG4, July 2005